BIA Terminal 2 Development Project (Phase II, Stage 2) Progressing to Meet the Post COVID-19 Tourism and Aviation Growth
BIA Terminal 2 Development Project is underway to
meet the future demands of the tourism and the aviation industry. Airport &
Aviation Services (Sri Lanka) (Private) Limited – (AASL) commenced the
construction of the BIA terminal 2 in December 2020 and the construction
activities are underway despite the challenges of COVID-19 global pandemic.
Project Progress: Package A
New
Passenger Terminal Building and Associated Works:
The
construction works of the new terminal 2 commenced on 15th December
2020 and it is expected to complete the project on 14th December
2023. Project Management Unit (PMU), AASL
together with the JV Japan Airport
Consultants (JAC)/Nippon Koei Co., Ltd. – (JAC/NK), the
consultants of the project and TAISEI Corporation, Japan, the contractor are
working towards the achievement of the objectives of the project.
“Preliminary works and soil
investigations for pile foundations have been completed. Clearing the areas for
main Terminal building by root balling existing trees and replanting, hoarding
for the construction area, boring and concreting of pile foundations for Main Terminal
Building & viaduct
(overhead entry and exit to Main Terminal Building) etc. are in progress.
Airside construction works are yet to start. Since the development activities
are taking place in an operational airport, it requires special prior approvals
by Aviation Authorities with operational impact, safety and security studies
with regard to the effect of construction activities on airport operations which
are being carried out by the contractor and the project consultant” said
Major General (Rtd.) G. A. Chandrasiri, Chairman AASL.
Package B: Construction of new Apron and Taxiways
Under
the Package B, construction works commenced on 25th April 2017 and
it was expected to be completed on 29th February 2020. However,
works delayed due to COVID-19 pandemic situations prevailed in the latter part
of its completion. The Contractor
has been able to complete 94% of the works and the remaining Polymer Modified
Asphalt overlaying will be completed within the next 4 months’ time. Once
completed, 23 new aircraft parking bases will be added to the new terminal.
BIA Terminal-2 Contributes to the Environmental
Sustainability
Explaining
the environmental aspects of the project, Mr. Aruna Warushahennadige, Director
Aviation Projects/Director AASL, said “BIA
Terminal 2 development project was recommended in 2014 under the environmental
pollution program. We have initiated a special program on ‘Tree Planting’ with
the special focus on highly efficient Oxygen emitting trees such as mango and
sandalwood. Because of this project, around 1200 trees are affected. However,
we are preserving 200 numbers of trees onsite and 300 trees are root balled. We
are replanting these trees at the lagoon area of 11 acres that belongs to
Airport and Aviation Services. We commenced the program on 27th
March 2021. Further, 1400 trees will be planted at Warallawaththa and St.
Sebastian Mawatha and Airport and Aviation has taken sustainable measures to
plant 2 trees for every single tree that
we have to remove due to this construction”.
Mr.
Aruna Warushahennadige further stated that for each and every construction activity such as piling works is carried out as per
the guidelines given with
the approval obtained from Central Environment Authority
(CEA) for the implementation of
the project and daily
environmental monitoring schedule done by National Research Organization (NBRO)
team. Under that air quality, water quality, noise, vibration and dust etc. are
monitored in all areas of the construction sites at regular intervals.
BIA Terminal 2-
Achieved the LEED Accreditation
BIA
Terminal 2 is designed to
get the LEED accreditation (Leadership in Energy and
Environmental Design) and the
present design has
all the features
to consider for
the silver status
going beyond the expectation as it was originally expected to receive
Bronze certification. With the construction
process and usage
of specified material
for the construction
combined with the overall
design we expect
to get the Gold
certification under
LEED accredition for the
Terminal 2 by
the completion of
the Project.The project is being
constructed preserving 30%
energy and 40%
water consumption.
Fly to new heights
Developing Colombo as a
destination for aviation and construction of the Terminal 2 of Bandaranaike
International Airport (BIA) had been a dire need for the country's
socio-economic development. Air
transportation today, determines a country's economic power and the successful
completion of these infrastructure projects automatically elevates our
country’s economic prosperity, by adding to its foreign exchange earnings, GDP,
creating new jobs, creating new industries, and expanding aviation, and
travel-related industries. Airports play a significant role in branding nations
and they act as catalysts for socio-economic prosperity. The
commencement of BIA Terminal 2 will be a giant step towards becoming an
aviation hub in the region. Sri Lanka will fly to new heights of the globe.